The unification of the energy system of Western Kazakhstan with the Unified Energy System of Kazakhstan. Construction of electric grid facilities
Energy
Funding status: Guarantee status: An agreement has been concluded to open a credit line
Information about KEGOC JSC
Project name | The unification of the energy system of Western Kazakhstan with the Unified Energy System of Kazakhstan. Construction of electric grid facilities | ||||
Project description |
Construction of a new 500 kV high-voltage line and modernization of key substations. The following facilities will be built as part of the project: 1. Construction of 500 kV overhead line «Karabatan - Ulke»; 2. Construction of an open 500 kV switchgear at the Kabatan substation; 3. Expansion of the 220 kV open switchgear at the Kabatan substation; 4. Expansion of the 500 kV open switchgear at Ulke substation. |
||||
Borrower Development Bank of Kazakhstan JSC | KEGOC JSC | ||||
Final beneficiaries |
NWF Samruk-Kazyna JSC, Unified Accumulative Pension Fund JSC, minority shareholders |
||||
Product | Electricity | ||||
Structure of project financing | Project cost | up to 201.789 bln ₸ | |||
Participation of Development Bank of Kazakhstan JSC, in the context of financing currencies |
up to 32 bln₸
|
||||
Personal Interest of the Borrower | 60.537 bln₸ | ||||
Interest of other creditors in the project financing | EBRD - 109.252 bln₸ | ||||
Terms of granting the financing instrument of Development Bank of Kazakhstan JSC | Funding currency |
Tenge |
|||
Type of financing instrument | Credit line | ||||
Rate of remuneration |
|
||||
Loan term | Up to 20 years | ||||
Funding source | The Bank's own and borrowed funds | ||||
Additional Information | Address | Astana, Almaty district, 59 Tauelsizdik ave. | |||