Nursultan Nazarbayev International Airport JSC

Reconstruction of Astana International Airport’s passenger terminal

Transport infrastructure

Funding status: Guarantee status: Assimilated

Information on Astana International Airport JSC

Project name Reconstruction of Astana International Airport’s passenger terminal
Project description Modernization of Astana International Airport, including construction of a new passenger terminal to increase the airport's capacity to 1 775 passengers per hour
Borrower Development Bank of Kazakhstan JSC Astana International Airport JSC
Final beneficiaries
Ministry of Industry and Infrastructural Development of the Republic of Kazakhstan
Services Airport services
Structure of project financing Project cost  90,4 bln ₸
Participation of Development Bank of Kazakhstan JSC, in the context of financing currencies
  1. 11 bln ₸, including:
Sublimit №1 – 3,18 млрд.тенге; Sublimit №2 – 7,82 bln tenge.
  1. 22,5 bln ₸
Participation in financing of the project of other creditors
56,9 bln ₸


Terms of granting the financing instrument of Development Bank of Kazakhstan JSC Funding currency KZT
Type of financing instrument Medium term and long term lending of investment project
Rate of remuneration
  1. Sublimit 1 – 7% per annum;
         Sublimit 2 – 11,1% per annum
  1. 10,99% per annum
Loan term
  1. Up to 14 years from the date of the commencement of the availability period
  2. 180 months (15 years) from the date of conclusion of the Agreement on opening a credit line
Funding source Own and attracted funds (including funds from the National Fund of the Republic of Kazakhstan)